We're Expanding ... Again!

amerilux building expansion 2017Since being formed in May 2004, AmeriLux International has expanded its current facility twice. In 2009, we expanded the distribution center and operations space, nearly doubling the physical plant size. In 2012, we completed another expansion to the distribution center; bringing the total square footage of operations space to just under 60,000 square feet.

This time, AmeriLux is adding an additional building. The 30,592 square foot facility is being built on the vacant property adjacent to our East De Pere location and will house our extensive inventory of multiwall polycarbonate products. The new building will have 161 unique storage locations; providing us the opportunity to improve our lot control, minimize double handling of material, and allow for a true FIFO inventory system.

Progress photos and updates will be added regularly, so check back often!

 

Expansion Update: April 27th, 2017

The steel has arrived! Over the next couple of weeks, the construction crew will assemble and erect the building’s steel frame. It’s going to be exciting to watch the new building materialize!

amerilux building expansion 2017amerilux building expansion 2017

 

Expansion Update: April 18th, 2017

Backfill process is complete. Steel for the new building is scheduled to be delivered next week. Site work continues on the storm water and foundation drainage system.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Expansion Update: April 13th, 2017

The expansion to the front parking lot is taking shape. Crews have been busy this week spreading gravel and packing it down. Soon we will have plenty of parking for employees and visitors.

amerilux building expansion 2017amerilux buidling expansion 2017amerilux building expansion 2017

 

Expansion Update: April 5th, 2017

Foundation walls are complete. The excavation crew is working hard. Backfilling is underway.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Expansion Update: March 29th, 2017

Things are starting to take shape as work continues on the foundation wall.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Expansion Update: March 23rd, 2017

Concrete reinforcing wall form work is underway and footing work continues. Some footings have been poured. The excavation crew continues to make progress on the parking lot expansion.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Expansion Update: March 20th, 2017

Dirt is on the move! The crew continues to excavate soil in the area that will be the expanded parking lot. Work on footings for the new building is underway.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Expansion Update: March 17th, 2017

The excavation crew has been busy moving a lot of dirt, preparing the site for the expansion of the front parking lot.

amerilux building expansion 2017amerilux buildign expansionamerilux building expansion 2017

 

Expansion Update: March 15th, 2017

Site work continues in preparation for the initial footing excavation.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Expansion Update: March 10th, 2017

Site preparation has begun! Heavy equipment moved in and the excavation crew began clearing the site of vegetation, brushwood, and other debris.

amerilux building expansion 2017amerilux building expansion 2017

 

 