In May of 2004, AmeriLux International moved into a 20,000 square feet facility located in De Pere’s East Industrial Park just south of Green Bay, Wisconsin. Since then, the AmeriLux campus has continued to grow and expand to meet its customer’s needs, deliver added value, and create ‘win-wins’.

In 2009, AmeriLux expanded its distribution center and operations space, nearly doubling the physical plant size. Another expansion to the facility was completed in 2012; bringing the total square footage of operations space to just under 60,000 square feet.

AmeriLux added ‘Building #2’ to its campus in 2017. The 30,000 square foot facility was built on vacant property adjacent to the main facilities East De Pere location and houses an extensive inventory of multiwall polycarbonate products.

This year brings another expansion. AmeriLux recently purchased the property next door at 1200 Enterprise Drive for a 25,000 square foot expansion to Building #2. The added space will increase storage capacity for an ever-growing product offering and create easy access to inventory for timely order fulfillment. The AmeriLux campus will soon total 135,000 square feet!

The Building #2 expansion project is expected to be finished by early 2020. Progress photos and updates will be added regularly, so check back often.

 

Building Expansion Update: March 20th, 2020

The AmeriLux A-team continues to move product into the new building expansion. They are doing a great job organizing the space for optimal storage and efficiency. Additional pallet racking is also being installed along the back wall. The crating department has settled into their new work area. All of this reorganization has created more space in Bldg #1 for component assembly, fabrication, and order fulfillment. When spring finally arrives in Wisconsin, the asphalt and landscaping work will be completed.    

AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020

AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020

AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020

 

Building Expansion Update: March 6th, 2020

The crew finished installing the cantilever racking and wire guidance system this week. This wire guidance transmits an electrical signal to the multidirectional side loader, enabling it to track a guidewire in the floor. Wire guiding increases productivity and reduces product and rack damage within aisles. The HUBTEX has already been busy moving material and filling the racks with long pallets of polycarbonate and PVC panels.

AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020

 

Building Expansion Update: February 28th, 2020

The crew was busy assembling and installing the cantilever racking this week. This is the same type of racking system that is currently installed in Building #2. Vertical racking systems like these save floor space, minimize the double handling of material, and allow for quicker order fulfillment.   

AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020

AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020

 

Building Expansion Update: February 21st, 2020

The contractor’s crew finished painting the last of the steel columns and have applied epoxy to seal the concrete floor. Truckloads of racking components arrived this week. Installation of the cantilever racking is scheduled to begin on Monday.

AmeriLux Buidling Expansion 2019-2020AmeriLux Buidling Expansion 2019-2020AmeriLux Buidling Expansion 2019-2020

 

Building Expansion Update: February 14th, 2020

The rest of the wall between the current building and the expansion came down this week, really opening up the space. Electrical and mechanical work continued and should be finished soon.

AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020

 

Building Expansion Update: February 7th, 2020

With the majority of the exterior work done, the crew is now focused on their interior task list. Insulation has been installed in the walls and ceiling. A portion of the wall between the current Bldg #2 and the expansion has been opened up. A temporary reinforced poly was put up where the THERMOCLICK™ panels were removed. The crew has begun painting the steel beams and columns a bright white. This will brighten the space and make it look cleaner.

AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020

AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020

 

Building Expansion Update: January 31st, 2020

The crew was hard at work this week finishing the installation of the roofing and the LEXAN™ THERMOCLICK™ 40mm blue panels on the side walls. All the doors, including the overhead doors, have also been installed. Now completely covered, Building #2 looks really large and tall!

AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020

AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020

 

Building Expansion Update: January 24th, 2020

The structure’s steel frame is now covered with metal siding and installation of the LEXAN™ THERMOCLICK™ panels is nearly complete. Incorporating natural light into an industrial building creates a more pleasant work environment and helps to reduce artificial lighting costs. Click here to learn more about this easy-to-install daylighting product.

AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020

AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020

 

Building Expansion Update: January 17th, 2020

The masonry crew was busy under their makeshift dome this week and completed the exterior brick wall. Installation of our 40mm Blue LEXAN™ THERMOCLICK™ interlocking sheet system began along the upper portion of the back wall as well as work started on the roof.

AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020

AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020

AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020

 

Building Expansion Update: January 10th, 2020

Visible progress was made this week with the installation of the metal siding panels on the exterior of the building. The front of the building expansion will feature a continuation of the brickwork. A crew will begin work on the masonry wall next week under the cover of a makeshift dome.

AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020

AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020

AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020AmeriLux Building Expansion 2019-2020

 

Building Expansion Update: January 3rd, 2020

The crew was busy this week adding bracing to the structural steel frame. The bracing provides additional strength and rigidity. This increases the buildings overall stability, preventing it from collapsing under structural loads such as wind, snow, and settlement.  

AmeriLux Buidling Expansion 2019-2020AmeriLux Buidling Expansion 2019-2020AmeriLux Buidling Expansion 2019-2020

AmeriLux Buidling Expansion 2019-2020AmeriLux Buidling Expansion 2019-2020AmeriLux Buidling Expansion 2019-2020

 

Building Expansion Update: December 27th, 2019

The crew operating the crane this week have been busy hoisting large steel beams into place. The structural steel frame for the roof is nearly finished. The immense size and form of the addition to Building #2 is becoming more visible. 

AmeriLux Buidling Expansion 2019AmeriLux Buidling Expansion 2019AmeriLux Buidling Expansion 2019

AmeriLux Buidling Expansion 2019AmeriLux Buidling Expansion 2019AmeriLux Buidling Expansion 2019

 

Building Expansion Update: December 20th, 2019

The steel frame for the expansion of Building #2 has started going up this week! The site has been busy with movement as the crane arrived earlier this week and the first of the steel framework has been raised and assembled. The expansion is progressing along nicely and taking dimensional shape.

AmeriLux Building Expanstion 2019AmeriLux Building Expanstion 2019AmeriLux Building Expanstion 2019

AmeriLux Building Expanstion 2019AmeriLux Building Expanstion 2019AmeriLux Building Expanstion 2019

AmeriLux Building Expanstion 2019AmeriLux Building Expanstion 2019AmeriLux Building Expanstion 2019

 

Building Expansion Update: December 13th, 2019

The construction site has been rather quiet the last couple of weeks, but that will soon change. A large crane is scheduled to arrive on Monday and the steel frame will start going up. It’s going to be exciting to see the expansion to Building #2 start to take shape and become more visible.

AmeriLux Building Expansion 2019AmeriLux Building Expansion 2019AmeriLux Building Expansion 2019

 

Building Expansion Update: November 27th, 2019

Several trucks arrived this week carrying the steel components for the building expansion. The forklift driver kept busy unloading and laying out the delivered materials. In a couple of weeks, the crew will begin assembling and erecting the building’s skeleton steel frame.

AmeriLux Building Expansion 2019AmeriLux Building Expansion 2019AmeriLux Building Expansion 2019

AmeriLux Building Expansion 2019AmeriLux Building Expansion 2019AmeriLux Building Expansion 2019

AmeriLux Building Expansion 2019AmeriLux Building Expansion 2019AmeriLux Building Expansion 2019

 

Building Expansion Update: November 22nd, 2019

Concrete work resumed this week. Aprons were poured in front of the two truck bays, creating an efficient loading dock space for large vehicles to be loaded or unloaded with material. In addition, concrete pads were poured for the exterior entrance doors as well as a walkway was installed around parts of the building perimeter.

AmeriLux Buidling Expan sion 2019AmeriLux Buidling Expan sion 2019AmeriLux Buidling Expan sion 2019

AmeriLux Buidling Expan sion 2019AmeriLux Buidling Expan sion 2019AmeriLux Buidling Expan sion 2019

AmeriLux Buidling Expan sion 2019AmeriLux Buidling Expan sion 2019AmeriLux Buidling Expan sion 2019

 

Building Expansion Update: November 15th, 2019

The construction site was rather quiet this week except for the presence of the excavation crew. The digger was busy reducing the piles of dirt and gravel and finishing up some site work. The backfill process in nearly complete. Water and sewer pipe work are underway.

AmeriLux Building Expansion 2019AmeriLux Building Expansion 2019AmeriLux Building Expansion 2019

AmeriLux Building Expansion 2019AmeriLux Building Expansion 2019AmeriLux Building Expansion 2019

 

Building Expansion Update: November 8th, 2019

Winter has arrived early in Wisconsin and the construction crews have been racing against Mother Nature. One after another, cement trucks continued to arrive this week to pour the remainder of the concrete slab. The interior floor for the building addition is now complete!

AmeriLux 2019 Buidling ExpansionAmeriLux 2019 Buidling ExpansionAmeriLux 2019 Buidling Expansion

AmeriLux 2019 Buidling ExpansionAmeriLux 2019 Buidling ExpansionAmeriLux 2019 Buidling Expansion

 

Building Expansion Update: November 1st, 2019

Under floor mechanicals have been setup. A portion of the site was prepared for concrete installation. Concrete formwork was built. A parade of cement mixers showed up mid-week to pour the first sections of the large concrete slab. Ground prep continues to move at a fast pace.

AmeriLux 2019 Building ExpansionAmeriLux 2019 Building ExpansionAmeriLux 2019 Building Expansion

AmeriLux 2019 Building ExpansionAmeriLux 2019 Building ExpansionAmeriLux 2019 Building Expansion

AmeriLux 2019 Building ExpansionAmeriLux 2019 Building ExpansionAmeriLux 2019 Building Expansion

 

Building Expansion Update: October 25th, 2019

The expansion to Building #2 is starting to take shape. The footings and foundation walls are complete with anchor bolts in place. Some backfilling is underway. It’s exciting to see how large this facility will be!

AmeriLux 019 Building ExpansionAmeriLux 019 Building ExpansionAmeriLux 019 Building Expansion

AmeriLux 019 Building ExpansionAmeriLux 019 Building ExpansionAmeriLux 019 Building Expansion

 

Building Expansion Update: October 18th, 2019

Work on the expansion to Building #2 is underway! Heavy equipment has moved in, the site has been cleared, and a lot of dirt has been moved. The crew is busy building the temporary formwork and installing the reinforcement supports (rebar) for the concrete footings and walls.

AmeriLux Building Expansion 2019AmeriLux Building Expansion 2019AmeriLux Building Expansion 2019

AmeriLux Building Expansion 2019AmeriLux Building Expansion 2019AmeriLux Building Expansion 2019

 

 

Back to homepage

Product Logos multiwall polycarbonate thermoclear verolite corrugated polycarbonate agrilite pvc liner panels trusscore lumira aerogel lexapanel standing seam